pgc all green working and signpost with lettering new colour 2
pgc all green working and signpost with lettering new colour 2
facebook icon twitter icon

Share this article share on facebook share on twitter

A105 Scheme

Green Dragon Lane to York Road - Most substantive work on this section is complete. The zebra crossing has now been connected and the associated road marking work will take place next week.

Borden Avenue to Walnut Grove - We will continue to install cycle segregation units until early April. Line marking will continue this week. The bus shelter outside the church will be replaced at a later date by Transport for London. Work is expected to be complete by the mid April.

Sainsbury's Junction - The traffic signals at the junction have been installed and are awaiting the completion of the power supply. Lane markings have been completed. Cycle segregation units will be installed by the end of April. Work is expected to be complete by the mid-May.

Station Road Junction - Work will continue on the installation of kerb lines, paving work and cycle lane. We are also installing three central islands. Surfacing work will take place from Monday 10 April for four nights under a road closure between 8pm and 5am. The work on this section is scheduled to be complete by mid May 2017.

Church Street Junction with Bush Hill Road - We have completed the construction of the bus stop outside 90 Ridge Avenue and will be constructing the footpath area behind this. We are currently working on the bus stop outside the park which is due to be completed next week. Most new street lighting has now been commissioned. Work on this section is expected to be complete by late April.

Lodge Drive to Osborne Road -  We will be working between Bourne Hill/Hedge Lane and Fox Lane roundabout in order to install the new cycle path. We will also be installing drainage, paving and signalling. More parking spaces have been made available for business customers in this area. Work on this section is scheduled to be completed by late May 2017.

Radcliffe Road to Riverbank - We are installing a new kerb line and cycle lane as well as improving drainage. The work on this section is scheduled to be completed by mid June 2017.

Oaktree Avenue to Highfield Road - Work to replace paving slabs and to create the cycle lane will take place over the next week. Work on the construction of two new bus shelters is now complete with work starting on a further stop near Fernleigh Road. Temporary pedestrian signals will remain place until the new crossing is commissioned. Work is expected to be complete by the end of April.

Ponders End scheme

End High Street - Work on the High Street is anticipated to start in early April 2017. The northern section between Eagle House Car Park and Stonehorse Road will be constructed in the first half of the calendar year. The southern section between Stonehorse Road and Clarence Road will be built in the second half of the calendar year. The challenging reconfiguration of the Derby Road junction is being planned for the summer holiday period to minimise disruption.
 
Queensway - Associated works are planned for Queensway to improve pedestrian access to the new school. The work to improve the footways and add a zebra crossing started earlier this month. This section is not expected to affect the wider traffic network.

To see the work schedules for all projects including those not yet started please visit our Construction Page.

Log in to comment
Clicky